Equinix SY1 Power maintenance
Scheduled Maintenance Report for M.D.G. IT
Completed
The scheduled maintenance has been completed.
Posted Jul 26, 2021 - 02:00 AEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 25, 2021 - 23:00 AEST
Update
Due to power works by Equinix in SY1 we will be redistributing power loads between 11pm AEST 25 July 2021 and 2am AEST 26 July. Customers may experience intermittent network degradation for several minutes during the maintenance window (update to affected components only)
Posted Jul 25, 2021 - 17:49 AEST
Scheduled
Due to power works by Equinix in SY1 we will be redistributing power loads between 11pm AEST 25 July 2021 and 2am AEST 26 July. Customers may experience intermittent network degradation for several minutes during the maintenance window.
Posted Jul 25, 2021 - 17:43 AEST
This scheduled maintenance affected: VPS Hosting, Sydney, Shared Hosting, Sydney, Client Area, Ticket Support, and Billing system.